ĐOKIĆ: CONSTRUCTION OF THREE SMALL HYDROPOWER PLANTS ACCORDING TO SCHEDULE

FOČA, APRIL 15 /SRNA/ - Three small hydropower plants on the Bistrica River near Foča are being intensively built and all works will be completed according to plan, by the end of 2026, said the Minister of Energy and Mining of Republika Srpska, Petar Đokić, who visited the construction site today.

FOČA, APRIL 15 /SRNA/ - Three small hydropower plants on the Bistrica River near Foča are being intensively built and all works will be completed according to plan, by the end of 2026, said the Minister of Energy and Mining of Republika Srpska, Petar Đokić, who visited the construction site today.



The total installed capacity of this system is 39 megawatts with a total annual production of 152 gigawatt-hours of electricity. Đokić says the project, based on a previously signed contract, is worth EUR 102,816,000. "We expect certain changes during the implementation, but in any case this project represents an exceptional value for the Republika Srpska energy system. The minister of energy praised the contractor - the Chinese AVIC Company for, as he said, the impressive feat of drilling 9,200 meters of tunnels out of the planned 9,800 meters. He has stated that the final internal works on the tunnels should now be carried out and that, according to the contractor's assessment, all works will be carried out within the planned work dynamics and the deadlines stipulated in the contract. Đokić emphasized the importance of this power plant for Foča as it would provide significant financial resources from the concession fee, while a certain number of people will remain to work in the area permanently. "It is useful that this power plant allows local subcontractors to be involved in different phases of implementation, which was one of our important goals - to accelerate the development of our construction operations and to train them in this way for some other, similar projects," emphasized Đokić. The Republika Srpska Government will not stop, he emphasized, adding that work is currently being carried out intensively on the much larger HPP Dabar near Nevesinje, with an installed capacity of 159 megawatts, whose completion is planned in 2027. According to him, the Chinese AVIC Company has demonstrated its construction capabilities in the previous phase and set an example for local contractors on how complex construction works can be carried out in difficult conditions. He added that the supervising body has no objections to the work carried out in the previous phase. Construction site manager Feng Zhou of AVIC noted that the project includes three small hydropower plants with 9,800 meters of tunnels. "There are only 600 meters of tunnels left to complete. We believe in the work dynamics of the project, that we will complete everything within the planned deadline, of course with the full support of Republika Srpska," said Sjong. The CEO of the HPP Bistrica Dejan Pavlović says this company currently has 28 employees from the municipality of Foča, and that the project is very important for the local community and Republika Srpska. "The dynamics of the works are more than excellent, 9.2 kilometers of tunnels have been completed, and it would have been even more, but the level of the Bistrica was quite high," said Pavlović and expressed confidence that all works will be carried out within the scheduled time. After visiting the site, Minister Đokić spoke with representatives of this corporation at the headquarters of the Chinese company in Foča about current issues in the implementation of the project to build three hydroelectric power plants on the Bistrica River. The Bistrica Hydropower Plant is an energy system consisting of three hydroelectric power plants with a total installed capacity of 34 megawatts. The Bistrica is a river that flows throughout the eastern part of Republika Srpska and is a left tributary of the Drina River. Hydropower plants B-1, B-2a and B3 are arranged in a staggered manner in the river downstream. The company HPP Bistrica Foča was formed with the aim of implementing this hydropower project on the Bistrica River.

English

Time1 hour from now

QUALIFYING MATCHES FOR THE ITF TOURNAMENT BEGIN TODAY

QUALIFYING MATCHES FOR THE ITF TOURNAMENT BEGIN TODAY

DOBOJ, MAY 17 /SRNA/ - Qualifying matches for the 2026 ITF M15 Doboj Open begin today in Doboj, featuring 44 competitors.

Time1 hour from now

CONCERT HELD IN GRAZ FOR THE STANKOVIĆ FAMILY FROM VRANJE

CONCERT HELD IN GRAZ FOR THE STANKOVIĆ FAMILY FROM VRANJE

GRAZ, MAY 17 /SRNA/ - The musical ensemble “Fenečki biseri” performed in Graz at a humanitarian concert, where funds were raised for the Stanković fam...

Time24 minutes from now

THREE PEOPLE ARRESTED IN ATHENS, COCAINE AND CANNABIS SEIZED

THREE PEOPLE ARRESTED IN ATHENS, COCAINE AND CANNABIS SEIZED

ATHENS, MAY 17 /SRNA/ - Large quantities of cocaine and cannabis, with an estimated street value of over 400,000 Euros, have been seized in Greece, an...

Time20 minutes from now

VUJIČIĆ: WITHDRAW ALL LAWS IMPOSED BY CHRISTIAN SCHMIDT

VUJIČIĆ: WITHDRAW ALL LAWS IMPOSED BY CHRISTIAN SCHMIDT

SARAJEVO, MAY 17 /SRNA/ - If BiH wants to survive and move in a normal direction, including towards the EU, it must withdraw all laws imposed by Chris...

Time13 minutes from now

CONSTRUCTION OF MAIN GAS PIPELINE AND HIGHWAY TO MLINIŠTA FOR A BETTER LIFE FOR CITIZENS

CONSTRUCTION OF MAIN GAS PIPELINE AND HIGHWAY TO MLINIŠTA FOR A BETTER LIFE FOR CITIZENS

BANJA LUKA, MAY 17 /SRNA/ - The goal of constructing the Šepak - Novi Grad main gas pipeline and the Glamočani-Banja Luka-Mliništa highway is to creat...

Time57 seconds from now

THEY ARE BUILDING A NATIONAL IDENTITY BY DENYING EVERYTHING SERBIAN

THEY ARE BUILDING A NATIONAL IDENTITY BY DENYING EVERYTHING SERBIAN

ISTOČNO SARAJEVO, MAY 17 /SRNA/ - Political scientist Filip Matić told SRNA that it is disappointing that parts of the Bosniak political elite, partic...

See all

Copyright © 2023 News Agency of the Republic of Srpska - Srna. All rights reserved. The content of these pages may not be transmitted without permission and without citing the source